This TIMELINE page will provide our viewers
with periodic progress of the facility.
June 2023 Breaking Ground!
The Project Begins! Ground leveling.
The USTA Hawaii Pacific broke ground on its USTA Hawaii Pacific Campus in EWA Beach, one of Oahu's fastest-growing communities.
December 2024Signing the Deed!
The USTA Hawaii Pacific/Executive Director, Ron Romano signs the deed to get the title to the property!
The USTA Hawaii Pacific and Rae Douglass Architects began work on the design & layout.
December 2024 The work begins!
The USTA Hawaii Pacific and Park Engineering signed an agreement to begin work on the property.
December 2024 The Campus design & layout
In Phase 1 of our project, The Campus design will include 8 tennis courts, a clubhouse, restrooms and a large parking lot.
December 2024 Informing the Community
Several Town Hall meetings were held in 2024 to inform the community of the upcoming campus
June 29, 2025The City & County of Honolulu approved the “Conditional Use Permit”
August 21, 2025Conceptual layout and building design in progress!